Project locations

The project is realized at the following sites:

Brno
VUT, Antonínská 548/1 – installation of data storage (disk array and tape library).

MU, Botanická 68a – installation of new core router functioning as an access PE router (medium terabit router) and components for collaboration environment.

České Budějovice

JČU, Branišovská 31 – installation of new core router functioning as an access PE router (medium terabit router).

Hradec Králové

LF UK, Šimkova 870 – installation of new core router functioning as a P router and of a new access PE router (large terabit router).

Jihlava

Krajský úřad Jihlava, Žižkova 57 – installation of data storage (disk array and tape library).

Liberec

TUL, Voroněžská 13 – installation of new core router functioning as an access PE router (medium terabit router)

Most

Střední škola technická, Dělnická 21 – extension of existing router configuration

Olomouc

UPOL, tř. Svobody 26, Nature Sciences campus – installation of new core router functioning as a P router and of a new access PE router (large terabit router)

Ostrava

VŠB, 17. listopadu 15 – installation of new core router functioning as an access PE router (medium terabit router)

Pardubice

UPa, ulice Studentská – installation of new core router functioning as an access PE router (small terabit router)

Plzeň

ZČU, Univerzitní 8 – installation of computing cluster, installation of data storage (disk array and tape library), and installation of new core router functioning as an access PE router (medium terabit router)

Ústí nad Labem

UJEP, České mládeže 8 – extension of existing router configuration

Zlín

UTB, nám. T. G. Masaryka 5555 – installation of new core router functioning as an access PE router (small terabit router)